Multiple crews will begin both projects at the same time on Monday May 13th.
For the plaza terrazzo sealer they will need 3 days to complete the work. They will power wash the plaza on the first day (Monday May 13th) and will need two days to apply the sealer in two separate phases (Tuesday and Wednesday May 14th & 15th). Workers are expected between 8am and 4pm. Commercial unit occupants in the mall and the first several floors of the residential units from the ’06 units around to the ’15 units will likely observe some noise as work is done and notice odors on the days the sealer is being applied.
The sealer application is weather dependent, so if it is too cold or raining, the work is expected to be delayed to the next day when the weather is cooperative. While they apply the sealer, so it can safely and properly set and cure, the North set of mall doors will be locked so that no one exiting the building will step into the fresh sealer. Similarly, the revolving doors and South exit will be closed off when that area is being done. We will also have the stairs by the bus stop on Sheridan road caution taped off as necessary.
For the 2nd Floor concrete decks, both around the garden planters and the Health Club, the Membrane will begin being replaced on Monday May 13th. Work will be performed weather permitting between 8am and 4pm. Commercial units should be aware there will be noise from time to time as they remove the old membranes. It is likely to be heard by all spaces at one point or another. Residential units facing the lake, up about 6-10 floors will likely hear some noise and may smell some fumes as the new membrane coating is applied.
Weather permitting, this work will unfold in three separate phases:
Phase 1 (the main deck around the gardens) May 13th – 22nd
Phase 2 (the area surrounding the kiddie pool) May 23rd – 30th
Phase 3 (exterior of the party room) May 31st – June 7th
While Phase 2 is underway, a 2nd contractor hired by the Board is expected to come out to replace the Heating and Cooling Unit for the Health Club weight room and racquetball court. This is being coordinated at the same time so the membrane can be properly applied underneath it. As soon as the membrane is done the new HVAC unit will be delivered and installed. (There will be no heating or cooling for the weight room and racquetball court for approximately 5-7 days.)
The range of temperatures we are expecting should be perfect for this work. It is really precipitation that will be the big question mark. Expect that one day of bad weather will tack on one day of additional time to the length of the projects.
We appreciate everyone’s patience and understanding while these planned improvements and important maintenance are coordinated.