We anticipate work to begin on floors 47 and 48 on Monday September 25th, and barring any unknowns, on 45 and 46 on Monday October 9th. The schedules should unfold similarly to the expected schedule below. Unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays (consistent with the schedule), between 9am and 5pm. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
For All Other Floors
Schedules are posted online at www.ptcondo.com, usually a few weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
We anticipate the hallway remodeling work to begin on floors 47 and 48 on Monday September 25th, and barring any unknowns, on 45 and 46 on Monday October 9th. The schedules are expected unfold similarly on all floors.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Monday September 25th
Both floors (47 and 48) carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday September 26th
Both floors (47 and 48) wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday September 27th
Both floors (47 and 48) wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday September 28th
Both floors (47 and 48) painting continuing with walls and trim, and installation of new baseboards begins.
Friday September 29th
Both floors (47 and 48) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday October 2nd
48th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday October 3rd
48th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday October 4th
48th floor carpet installation
47th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday October 5th
47th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday October 6th
47th floor carpet installation.
Monday October 9th – New light fixtures to be installed on 48th floor. Work gets underway on floors 45 and 46.
Tuesday October 10th – New light fixtures to be installed on 47th floor.
Thereafter our team will be addressing any punchlist items, and the week of October 9th we anticipate there to be some touch ups throughout both hallways. We would also expect by then that detailed schedules will be out for the 45th & 46th floors, and work should be getting underway similar to the above schedule on Monday October 9th.
The schedules for each floor should unfold similarly to the 47th and 48th Floors. Work on unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
We anticipate work to begin on floors 49 and 50 on Monday September 11th, and barring any unknowns, on 47 and 48 on Monday September 25th. The schedules should unfold similarly to the expected schedule below. Unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
For All Other Floors
Schedules are posted online at www.ptcondo.com, usually a few weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
We anticipate the hallway remodeling work to begin on floors 49 and 50 on Monday September 11th, and barring any unknowns, on 47 and 48 on Monday September 25th. The schedules will unfold similarly to the 51st and 52nds Floors.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Monday September 11th
Both floors (49 and 50) carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday September 12th
Both floors (49 and 50) wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday September 13th
Both floors (49 and 50) wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday September 14th
Both floors (49 and 50) painting continuing with walls and trim, and installation new baseboards begins.
Friday September 15th
Both floors (49 and 50) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday September 18th
50th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Tuesday September 19th
50th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Wednesday September 20th
50th floor carpet installation
49th floor, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Thursday September 21st
49th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Friday September 22nd
49th floor carpet installation.
Monday September 25th – New light fixtures to be installed on 50th floor.
Tuesday September 26th – New light fixtures to be installed on 49th floor.
Thereafter our team will be addressing any punchlist items, and the week of September 25th we anticipate there to be some touch ups throughout both hallways. We would also expect by then that detailed schedules will be out for the 47th & 48th floors, and work should be getting underway similar to the above schedule on Monday September 25th.
The schedules for each floor should unfold similarly to the 49th and 50th Floors. Work on unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
We anticipate work to begin on floors 49 and 50 on Monday September 11th, and barring any unknowns, on 47 and 48 on Monday September 25th. The schedules will unfold similarly to the 51st and 52nds Floors, however without Labor Day. work on unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. See the schedule below for reference.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
As Anticipated, The Updates To Floors 54 And 53 Should Start On Monday August 14th – Details Below In the Original Post.
After that, we will be working from the 52nd floor down, until all hallways have been remodeled. The progress and activity for the 52nd and 51st floors, getting underway Monday August 28th, is expected to unfold as follows:
Monday August 28th
Both floors carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday August 29th
Both floors wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday August 30th
Both floors wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday August 31st
Both floors painting continuing with walls and trim, and installation new baseboards begins.
Friday September 1st
Both floors complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday September 4th – Labor Day (no work)
Tuesday September 5th
52nd floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Wednesday September 6th
52nd floor carpet installation.
52nd floor, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
51st floor sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Thursday September 7th
51st floor sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Friday September 8th
51nd floor carpet installation.
Monday September 11th – New light fixtures to be installed on 52nd floor.
Tuesday September 12th – New light fixtures to be installed on 51st floor.
Thereafter our team will be addressing any punchlist items, and the week of September 11th we would expect there to be some touch ups throughout both hallways. We would also expect by then schedules will be out for the 49th & 50th floors, an work should be getting underway similar to the above schedule on Monday September 11th.
Work is expected to continue after that with the 52nd and 51st Floors, Monday August 28th
Consistent with the results of the recent survey, the PTCA Home Improvement Commission chose to recommend the design of the 55th Floor. This was approved by the Board of Directors at the June 12th Board Meeting and that means there will be some changes made on 53 and 54.
Our team placed orders for materials right away. Much has already been delivered for the bulk of what we need and after coordinating with the contractors, work has been scheduled.
Below is the anticipated schedule of work and activity for the 54th and 53rd Floors. Keep in mind, this is preliminary and subject to change if any unforeseen events or conditions are encountered.
For residents of these floors during this period of time, expect workers to be coming and going, periodic noise throughout the day, some dust, some odors when there is painting and gluing, and your entry doors will be open on days when sanding, priming and painting is done. This time, there will only be a light sanding of the doors, so that the new paint will sufficiently bond with the door.
Feel free to reach out to the office with any questions you may have, at 773-769-3250 or by e-mail at parktowercondo-mgmt@habitat.com. If you aren’t already on our list, let us know you to join the Park Tower e-mail group to receive news, regular updates, announcements and notices.
Hallway Remodeling Schedule
54th and 53rd Floors
PLEASE NOTE, the following schedule is based on our present expectations and is subject to change unexpectedly. We will do our best to reach out to residents as quickly as possible should that happen.
August 14th-16th Monday-Wednesday
54th Floor painting and wallpaper.
August 17th Thursday
54th Floor Unit doors light sanding and repaint. Unit doors will be open. An employee of Park Tower will be present at all times.
August 18th, 21st & 22nd Friday, Monday & Tuesday
53rd Floor painting and wallpaper.
August 23rd Wednesday
53rd Floor Unit doors light sanding and repaint. Unit doors will be open. An employee of Park Tower will be present at all times.
August 24th & 25th Thursday and Friday
53rd and 54th Floor Carpeting alterations.