1 2 3 4 5
  • July 30, 2021

    Garage Project Reaches Major Completion! But…

    UPDATED July 30th The final walk through with the contractor was completed this week, and there are a few areas of minor work the contractor will need complete. On Thursday July 29th, our building engineers, Management, reps with the contractor and the engineering firm WJE met to do a complete walk through of the garage. […]

  • July 29, 2021

    See Something? Say Something!

    See A Problem? Have Suggestions for Business, Repairs, Or Improvements? Owners And Residents Are Encouraged And Welcome To Share Any Observations And Suggestions They Have As they say, if you see something, please say something! It is particularly important if you observe a problem, such as a maintenance or plumbing issue. Perhaps a hole in […]

  • July 29, 2021

    Sheridan Road Resurfacing and Train Modernization

    UPDATE Shared by ASCO – July 29th July 29, 2021 Dear Neighbor, This weekend Bryn Mawr Ave. will be closed between Broadway and Winthrop to allow crews to begin demolition on the viaduct. This will be an ongoing closure beginning tomorrow, Friday, July 30, 8pm, through Monday, August 2, 5am. This closure will also impact sidewalks. Crews […]

  • July 28, 2021

    RCN Cable/Internet Outage Tuesday July 27th

    UPDATED July 30th We had a few questions about the outage on Tuesday evening – and as always, when events such as this occur, we welcome and encourage our Owners and residents to address any questions or concerns with us. Where did this alleged squirrel chewing occur? We were advised by RCN this occurred along […]

  • July 28, 2021

    RISER PROJECTS DELAYED!

    UPDATED July 28th The start date for the ’07/’08 Bathrooms from 30 to 55 has been bumped to Monday September 13th, and tentatively for the ’06 Kitchens from 30 to 55, Monday November 1st. In April and May our team began efforts related to the Riser Projects for the ‘07/’08 high zone bathrooms, the ’06 […]

https://www.ptcondo.com/wp-content/themes/magpress