Phase II 52% Complete; Masonry and Tuckpointing 55% Complete Work on the driveway slowed unexpectedly this week. Testing was done on the concrete patches, and unfortunately it was not ready to accept the new membrane. The testing determines whether the concrete has adequately “cured”, which is when enough moisture has disipated. Despite near perfect weather, it was too […]
PARK TOWER CONDOMINIUM ASSOCIATION BOARD OF DIRECTORS MEETING Monday October 27, 2014 6:30PM: CLOSED SESSION The Board Discussed pending litigation, personnel, and violations of rules and regulations (Condominium Act – Sec. 18, a. 9). 7:30PM: OWNERS FORUM The Board and Management addressed questions and feedback from Unit Owners present. 7:50 PM: OPEN SESSION – Call to […]
Sadly, our Office Administrative Assistant Jenny Garcia has resigned from her position with Park Tower. She has been with us for just under 6 years. She was the friendly voice on the phone and the smiling face that greeted residents and Owners most of the time over these years. She was also responsible to work […]
PHASE 2 at 50% Complete, MASONRY at 50% Complete We were blessed with perfect weather this week, and very thankfully it appears the bulk of next week will be cooperative as well. The contractor has reported that they are done grinding the mortar joints along the brick wall and have already started to “point”. That […]
SB2664 IS STILL AN ISSUE Please Write Our Legislators We have the opportunity to relieve some of the undue burden foreclosures place on association budgets. At the last Board Meeting, the Board approved writing of uncollectible debt (assessments and fees due from owners who foreclosed or went bankrupt) over $33,000. Last year over $50,000 was written off. This […]
Phase 2 – 46% Complete, Masonry and Tuckpointing 25% Complete Preparations for new concrete on Phase 2 – in and around the Circle Driveway continued. The bad news was the rainy weather which slowed progress this week. Fortunately though, our contractor found an alternate source and supplier for concrete, with the material we need. So we expect during […]